Velcro USA Building 3 locker rooms and restrooms
Gut renovation of the men's and women's restrooms and locker rooms in Building 3 of Velcro USA's Manchester plant.
Town: Manchester, NH · Owner: Velcro USA · Scope: restroom and locker room renovation, plumbing, masonry
Solid Roots gutted the men's and women's restrooms and locker rooms in Building 3 of Velcro USA's Manchester plant. We demolished CMU walls and fixtures, made sewer main repairs, and cut about 480 SF of slab for new in-slab plumbing, then re-poured it. New masonry walls, metal-stud framing and drywall, doors and acoustical ceilings followed, with new wall-hung toilets, urinals, sensor-faucet sinks and ADA stalls. Finishes were an epoxy floor system in the restrooms, VCT in the locker rooms, epoxy cove base, partitions, mirrors and paint, with sprinkler, heating and electrical rework.